Housing Policy

Building Through the Storm

San José is making a counter-cyclical bet that cities do not have to wait for markets to self-correct, using targeted, temporary fee relief to drive the production of more than 4,000 housing units by 2027.

By Konstantin Voronin 12 min read January 15, 2026

TL;DR: San José's Counter-Cyclical Fee Relief

When the Storm Is Now

In 1923, John Maynard Keynes offered a critique of economists who counseled patience during economic crises:

"The long run is a misleading guide to current affairs. In the long run we are all dead. Economists set themselves too easy, too useless a task if in tempestuous seasons they can only tell us that when the storm is past, the ocean is flat again."
— John Maynard Keynes, A Tract on Monetary Reform (1923)

The housing market will eventually self-correct. Interest rates will moderate. Construction costs will stabilize. Capital will flow back into development. Given enough time, supply and demand will find equilibrium.

But families paying 50% of their income in rent can't wait for calm seas. Nurses doubling up in shared apartments can't wait. Teachers commuting two hours each way can't wait. The crisis is now.

San José decided not to wait.

The Stakes

More than half of San José renter households are cost-burdened, spending over 30% of their income on housing. For many, that number exceeds 50%. The teachers staffing classrooms, nurses working hospital shifts, retail employees serving customers: the essential workforce that keeps the city running faces an increasingly impossible housing market.

The math is unforgiving. A one-bedroom apartment averaging $2,638/month requires over $105,000 in annual household income just to stay below the cost-burdened threshold. That's out of reach for a significant share of the workforce.

There's only one durable solution to a housing shortage: build more housing. Increased supply, over time, moderates price growth and expands options for households at every income level. But in San José, market-rate housing production has nearly stopped in 2024.

When Markets Stall

Between 2020 and 2024, San José developers submitted applications for nearly 29,000 multifamily housing units. About 22,000 were entitled. Only 7,200 pulled building permits. The gap between approval and construction isn't regulatory, it's financial.

~29k
Units Submitted
~22k
Units Entitled
~7k
Permits Pulled

Source: California HCD Housing Element Implementation Dashboard, 2020–2024, 5+ unit structures.

The city's 2025 Cost of Residential Development Study documents why: construction costs consume roughly 69% of total development costs. San José achieves rents 10–15% below Peninsula markets, but construction costs are identical. For higher-density buildings, the apartments that could house thousands, projected revenues don't cover projected costs.

The result: zero new market-rate housing construction starts in 2024, prior to the Multifamily Housing Incentive Program (MHIP) implementation.

This isn't a San José-specific failure. It's what happens when interest rates rise, construction costs remain elevated, and achievable rents can't bridge the gap. Markets are cyclical. Sometimes the economics work; sometimes they don't.

The question for cities: wait for conditions to improve on their own, or act with the tools available?

What Cities Can Control

Cities don't set interest rates. They can't dictate lumber prices or labor costs. They have limited influence over investor return requirements or insurance premiums.

But cities do control development fees, tax rates, and inclusionary housing requirements. And when projects are 5-15% away from feasibility, as San José's study found for mid-rise buildings, adjusting these city-controlled costs can mean the difference between a stalled project and one that breaks ground.

This is the premise behind two programs coming to City Council on January 27, 2026:

What is the San José targeted fee relief program? The San José targeted fee relief program is a multi-phase policy intervention designed to stimulate high-density residential development. By temporarily reducing construction taxes by up to 50% and adjusting Inclusionary Housing Ordinance (IHO) compliance to 5% at 110% AMI, the policy aims to restore project underwriting feasibility during periods of high interest rates and stagnant market rents.

📊

Two Programs, One Goal

Promoting rental housing production

Program Target Location Capacity
MHIP Extension High-density rental (50+ du/acre) City-wide 3,600 units (Phase 1)
Conversion Program Office-to-residential (20+ units) Downtown 500 units (Phase 1)
📍

Incentive Program Pipeline

MHIP and Downtown Conversion Project Locations

MHIP
Conversion
Under Construction

Combined, these programs aim to unlock over 4,000 units of rental housing production over two years—housing that likely wouldn't get built under current market conditions without intervention.

Both programs apply to rental housing only. For-sale affordable housing continues to be addressed through the Inclusionary Housing Ordinance, which is also coming before Council on January 27.


The Case for Acting Now

Keynes's broader point, that governments should act counter-cyclically rather than waiting for markets to self-correct, finds support across economic and policy literature. When private sector activity falters, government can adjust policies to maintain production. The alternative, allowing construction to cease entirely, creates supply shortages that compound affordability problems for years.

Charles Lindblom and Albert Hirschman offered complementary frameworks: effective policy evolves through targeted adjustments rather than comprehensive overhauls, focused on specific bottlenecks within government's control. San José's approach reflects both principles. These aren't permanent programs that will benefit all future development. They're temporary, targeted interventions for a specific market moment. Eligible projects are those that have been entitled for years but remain stuck in the pipeline, unable to secure financing under current conditions. To qualify, developers must demonstrate that city fee relief will bridge the feasibility gap, consistent with the 2025 Cost of Residential Development Study findings.

The benefits extend beyond housing production. Projects that break ground generate construction jobs, property tax revenue once completed, and economic activity in surrounding neighborhoods. For downtown conversions especially, activating vacant office buildings supports broader revitalization goals in key growth areas.

The early evidence supports this approach. After zero market-rate starts in 2024, MHIP implementation helped restart the pipeline: 1,444 units are now under construction across five projects, representing over $20 million in fee relief and 228 deed-restricted affordable units that wouldn't exist if those projects hadn't moved forward.

Deeply Affordable Housing Continues Separately

These incentive programs target middle-income households earning 80–120% AMI, a segment often caught between subsidized housing and market rents. They don't replace or compete with the city's deeply affordable housing production.

San José continues to fund housing for lower-income households through dedicated programs:

The Housing Department currently has over 1,000 units at 30%, 50%, and 60% AMI levels moving toward completion, with additional closings expected in the coming months. These programs use different funding sources, including federal grants, state tax credit equity, and local housing trust funds, to serve households with the greatest need.

The two approaches are complementary: incentive programs restart market-rate production that had stalled entirely, while dedicated affordable housing programs continue serving lower-income households through separate funding streams.

MHIP Extension: Expanding What's Working

The Multifamily Housing Incentive Program launched in late 2024 as a direct response to stalled housing production. The premise was simple: if fee relief could tip marginally infeasible projects into viability, the city would see housing starts resume. The early results validated that theory.

The January 27 proposal extends the program through February 2027 and expands Phase 1 capacity. The original 1,800-unit allocation is nearly exhausted, with 1,444 units already under construction. The extension adds 1,800 new Phase 1 slots, bringing total 2026 capacity to approximately 2,156 units (356 remaining from 2025 plus 1,800 new).

The projects using these tools are on the ground now. Coyote Creek Village, the 1,430-home masterplan at Montague and Seely, shows the incentive stack at work across four product types, while the 195-unit affordable tower at Berryessa BART shows the eleven-source capital stack a project needs when fee relief alone isn't enough.

Phase 1 Benefits (First 3,600 units)

Eligibility Requirements

Projected Market-Rate Rents

MHIP projects are required to deed-restrict 5% of units at rents affordable to households earning 110% of Area Median Income. But even the remaining market-rate units are projected to serve middle-income households.

Based on developer underwriting and city rent surveys, market-rate rents in MHIP projects are expected to fall within the 80–120% AMI band, serving the workforce households who often earn too much for subsidized housing but struggle with market rents. See the 2025 San José Income and Rent Limits for current thresholds.

The city now runs a demand-side companion to these supply incentives aimed at the same workforce band: through LIVE San José, it master-leased 197 units in The Fay, a stalled downtown tower, and rents them to households at 80–110% of AMI — the renter's view is in the guide to LIVE San José at Flow.

Downtown Conversions: A Different Path to Housing

Downtown San José has over 20% office vacancy, a post-pandemic reality showing no signs of full reversal. The new Downtown Commercial-to-Residential Conversion Program aims to transform this challenge into housing opportunity.

But not every vacant office building can become housing. Physical form is decisive. The 2025 Cost of Residential Development Study dedicates an entire chapter to office-to-residential conversions, and the conclusion is stark: only a narrow subset of buildings can feasibly support this type of adaptive reuse.

Gensler, which has assessed over 1,300 potential conversion projects across 130+ cities, finds similar results nationally. Only 25–30% of buildings analyzed are physically suitable for conversion. And of those, roughly 5% are actually moving forward, as the gap between physical viability and financial feasibility remains wide.

What Makes a Building Convertible?

The buildings that work share specific physical DNA: narrow floorplates (40–60 feet deep) that give every unit windows, high ceilings (11–14 feet) that accommodate new mechanical systems, and punched operable windows that meet light-and-air codes without expensive facade modifications. Pre-1960s construction typically has these traits. Modern glass curtain-wall towers typically don't.

I've written a deeper analysis of the physical and financial factors that determine conversion feasibility: Good Bones: What Makes an Office Building Convertible?

The Financial Case

For buildings with the right geometry, conversion offers potential advantages. The Cost of Development Study notes that adaptive reuse can reduce construction timelines by avoiding lengthy entitlement processes for ground-up projects. However, the study also cautions that conversion costs are higher than many expect. Selective demolition, full systems replacement, and extensive tenant improvement work often narrow the cost differential between conversion and new construction.

San José has completed zero office-to-residential conversions to date. Three proposed projects are now positioned to change that.

Phase 1 Benefits (First 500 units)

Eligibility Requirements

Projected Rents Serve Workforce Households

Conversion projects are required to deed-restrict 5% of units at rents affordable to households earning 110% of Area Median Income. But the city's analysis shows that even market-rate rents in these projects will serve middle-income workers.

Key Dates

📅

Important Deadlines

Mark Your Calendar

Milestone Date
City Council Consideration ("Housing Day") January 27, 2026
Conversion Phase 1 Permit Deadline December 31, 2026
MHIP Phase 1 Permit Deadline February 28, 2027

For Developers: Evaluating Fit

MHIP Eligibility

Conversion Program Eligibility

Key Takeaways

  1. Zero market-rate starts in 2024 before MHIP—now 1,444 units under construction across 5 projects.
  2. Two programs, one goal: MHIP targets high-density rental, Conversion Program targets office-to-residential downtown.
  3. Over 10,000 units in the pipeline across both programs.
  4. Temporary and targeted: Phase 1 deadlines enforce time limits.

Questions or corrections? Reach me at kostya@kostya.io or LinkedIn.

Related Articles

Beyond Zoning: Why 22,000 Entitled Homes Are Waiting
Good Bones: What Makes an Office Building Convertible?
The BMR Pricing Formula
The Fourth Lever: 197 Workforce Apartments Without Pouring Concrete
Opportunity Zones 2.0 in San José & California: the 2027 Map and Non-Conformity Calculator

Konstantin Voronin

Konstantin is a Housing Planning and Policy Administrator for the City of San José, with prior experience in real estate development and proptech. He writes from the intersection of housing policy, development economics, and real estate technology in the Bay Area.

Disclaimer: The views and analysis expressed in this article are entirely my own and do not reflect the official policy or position of the City of San José.

Share
Link copied to clipboard!