TL;DR

For most of a century, the corner of Montague Expressway and Seely Avenue grew fruit. The Sakauye family farmed it through the decades in which every parcel around them turned to office park - Eiichi "Ed" Sakauye returned to the land after wartime internment and tended it for the rest of his working life. The holdout ended in January 2025, when the family and their neighbors, the Karolewskis, sold 22 acres for $78.6 million.4 The 1920 farmhouse made the eight-mile move to History Park this spring, where preservation groups are raising a further $300,000 to renovate its interior as exhibit and gallery space.1

What replaces the orchard is Coyote Creek Village, a 22.88-acre masterplanned mixed-use development that includes six distinct land uses:2

As of July 2026, 1,059 of the plan's 1,430 homes are under construction, with the townhomes currently pre-selling.

Coyote Creek Village is pouring foundations into a market that has stalled nearly everything else. Between 2020 and 2024, San José entitled roughly 22,000 homes; about 7,000 pulled building permits, and some 15,000 sit approved and unbuilt, waiting on economics rather than approvals - the feasibility gap examined in Beyond Zoning. This site pays the same construction costs and borrows from the same banks as the homes that stalled. What separates it is how the deal is built, starting with who holds which piece of the plan.

Who's building what, and when

Three developers hold three pieces of the plan, each with its own product, its own lender, and its own clock.

Component Developer Homes Status
Hanover Parkside (Building A) Hanover Company 397 Under construction; completion expected Q4 2027
Hanover Coyote Creek (Building B) Hanover Company 372 Construction starting July 2026
Building C Hanover Company 371 Future phase; no published schedule
Pyrus Place townhomes SummerHill Homes 154 Pre-selling; sales office at 675 Epic Way
Trimble Apartments (Phase 3, affordable) The Pacific Companies 136 State bond and tax credit award December 2025; construction expected summer 20263
Aerial view of the site before demolition - the Sakauye farm's orchard rows, farmhouse cluster, and fallow fields beside Coyote Creek The same aerial with the masterplan's parcelization overlaid - townhomes, Buildings A, B, and C, the affordable parcel, and the central park
Existing
Proposed

Hanover Parkside (Building A)

The first vertical building is a six-story wrap with 397 apartments - 377 market-rate and 20 income-restricted - over roughly 6,400 square feet of ground-floor retail, with parking integrated above grade. KTGY designed all three market-rate buildings; unit plans run from studios to three-bedrooms. Hanover lined up its financing at the land closing - a $120.4 million construction loan from JPMorgan Chase, recorded February 13, 2025 - and broke ground in October 2025.4 Completion is expected in the fourth quarter of 2027, with first occupancies to follow.

Hanover Coyote Creek (Building B)

The second building is seven stories: 372 apartments (353 market-rate, 19 income-restricted) over about 5,300 square feet of retail. On June 23, 2026, City Council approved its incentive package under the Multifamily Housing Incentive Program - more on that below - and the Council memo lists a July 2026 construction start.

Building C

Building C, at 371 units with 18 income-restricted, has no published schedule. Per the June memo, its application may come forward for future consideration as construction progresses, provided allocation remains available under the program's unit cap.

Pyrus Place townhomes

SummerHill Homes paid $73.6 million for roughly seven acres in January 2025 - within days of Hanover's $78.6 million purchase of the full site from the Sakauye and Karolewski families - and financed the phase with $61.2 million in construction financing from U.S. Bank.5 The 154 three-story townhomes come in five plans from 1,355 to 2,315 square feet, all three- or four-bedroom with up to 3.5 baths; the 1,827-square-foot Plan 3 adds a dedicated office, and every plan carries a two-car or tandem garage. The community is pre-selling through a sales office open weekends at 675 Epic Way and a marketing site at pyrusplace.com; a price sheet hasn't been published. HOA dues are estimated at $327 to $400 a month at full build-out. SummerHill chose to pay the Inclusionary Housing Ordinance in-lieu fee rather than provide BMR units on site.

The townhome neighborhood gets its own dog park and a small gathering park alongside direct access to the Coyote Creek Trail, and the family pitch leans on the new Agnews school campus 1.9 miles away - Abram Agnews Elementary, Dolores Huerta Middle, and Kathleen MacDonald High. The employment pitch is proximity: SummerHill's marketing lists Cadence half a mile away, Cisco at 1.4 miles, Apple's North San José campus at 2.2, Milpitas BART at 3.0, and the airport at 2.9.6 On the site plan, townhome addresses will sit on Sakauye Park Drive; the smaller lanes are named Pyrus - the pear genus the community takes its name from - Hachiya, a persimmon variety, and Okame, a flowering cherry, alongside Ayako Lane, Kimiko Lane, and Isao Drive.

Trimble Apartments (the affordable building)

The affordable building runs on a different engine entirely. The Pacific Companies will develop the plan's third phase as Trimble Apartments: 136 units on 1.25 acres at the northwest corner of Seely and Montague, all income-restricted apart from one manager's unit. In December 2025, the state awarded the project $31 million in tax-exempt bond authority and $5.47 million in annual federal 4% tax credits.7 The staff report puts total development cost at $115.9 million - $851,879 per unit - with construction anticipated from May 2026 to May 2028.3 The developer of record is Pacific West Communities, Inc.; Citibank and Bonneville are the lenders, Boston Financial is the tax credit investor, the California Municipal Finance Authority is the bond issuer, and the Central Valley Coalition for Affordable Housing is the nonprofit general partner alongside a Pacific affiliate.

Two things distinguish the deal from a typical San José affordable stack. The application lists no City or County soft loans: the permanent sources are the bonds, $44.9 million in tax credit equity, $8.5 million in deferred developer fee, and an $8.6 million donated land value, meaning the parcel comes to the partnership without a purchase.7 And the building uses the Average Income structure, with the 135 restricted units spread from 30% to 70% of area median income and the largest tier - 59 units - at 70% AMI. Higher average rents carry more debt, which is part of how the deal closes without local subsidy. The rent schedule shows what that means in dollars: a 70% AMI three-bedroom is proposed at $3,656 a month including utilities, against $1,567 for the same floor plan at 30% AMI. For the fully subsidized version of this product type, see the RISE / Berryessa case study: $897,528 per unit and eleven funding sources, four of them public soft loans. The June Council memo carves Trimble's units out of the MHIP allocation entirely, since fully affordable projects don't draw on the program's unit cap.

The masterplan's obligations run beyond housing. A 2.5-acre public park sits at the center of the apartment block, the plan includes what the district's councilmember has described as North San José's first dog park, pathways connect to the Coyote Creek Trail, and the landscape plan calls for 1,085 replacement trees against the 584 removed.

The affordable housing components, explained

Press coverage rounds the project to "1,430 homes." The affordability obligations behind it run through three separate mechanisms, all governed by a single Inclusionary Housing Agreement recorded against the site.

57 income-restricted apartments inside the market-rate buildings. Hanover's three buildings satisfy the Inclusionary Housing Ordinance through its mixed compliance option: 5% of units on-site with restricted rents - 20 in Parkside, 19 in Coyote Creek, 18 in Building C - paired with an in-lieu fee, which MHIP reduces to zero. These are moderate-income units: Building A's were approved with rents at or below 100% of area median income, Building B's at or below 110%.8 Income limits are published annually; eligibility for specific units is determined under the recorded agreement by the properties' managers once leasing begins.

The in-lieu fee on the Pyrus Place townhomes. SummerHill elected to satisfy the Inclusionary Housing Ordinance for the for-sale phase by paying the in-lieu fee rather than building BMR units on site. The MHIP relief that zeroes the fee for the rental buildings doesn't reach this phase - the townhomes are expressly ineligible for the incentive.

The 136 units at Trimble Apartments. Deeper affordability at scale, delivered by a specialist affordable developer as its own phase with its own capital stack, outside both the market-rate buildings' compliance math and the MHIP allocation. The mix is 64 one-bedroom, 37 two-bedroom, and 35 three-bedroom apartments, with the restricted units reserved for households earning 30% to 70% of area median income under a 55-year regulatory agreement.

The 135 restricted units by tier: 15 at 30% AMI, 15 at 50%, 46 at 60%, and 59 at 70%, with 2025 proposed rents from the state application. The unrestricted manager's unit is the thirty-seventh two-bedroom.

Unit type Units AMI tier Proposed rent (incl. utilities)
1 bedroom 12 30% $1,130
1 bedroom 12 50% $1,884
1 bedroom 20 60% $2,261
1 bedroom 20 70% $2,638
2 bedroom 2 30% $1,356
2 bedroom 2 50% $2,261
2 bedroom 14 60% $2,713
2 bedroom 18 70% $3,165
3 bedroom 1 30% $1,567
3 bedroom 1 50% $2,611
3 bedroom 12 60% $3,134
3 bedroom 21 70% $3,656

The incentive structure behind the project

Hanover's Buildings A and B each received Council-approved waivers under the Multifamily Housing Incentive Program. Trimble Apartments, the affordable building, appears in the program's progress reporting with no Council action of its own - and with the footnote that its units sit outside the program's unit allocation, since the project is entirely affordable.

MHIP is a temporary intervention: a program built to restart housing construction that had stalled under market conditions - high interest rates, elevated construction costs, flat rents. Council adopted it in December 2024 for projects that had their approvals but could not raise construction financing, and put a deadline on the benefit: originally, a building permit by the end of 2025. It has extended the term twice since - raising the unit cap in May 2025, then again in January 2026, when it also pushed the Phase I deadline to February 28, 2027.

The Seely sequence, from entitlement to today:

The two approved waivers, side by side:

  Building A Building B
Council approval June 17, 2025 June 23, 2026
Units (income-restricted) 397 (20) 372 (19)
Net residential square footage 347,856 325,109
IHO in-lieu fee waived $4,800,413 $4,480,002
Construction tax reduction $1,257,124 $1,773,456
Total waiver $6,057,537 $6,253,458
Per unit9 $15,258 $16,810

Each building applies for its own waiver as its financing comes together, rather than the masterplan taking the full benefit up front. Anything above $1 million goes to a public hearing noticed 28 days in advance, which is why Buildings A and B each went to a vote, and why a construction-tax reduction for Trimble's 136 units did not. Approval is not the end of the City's involvement either - the resolution authorizes construction progress agreements, and staff monitor building work against the program's requirements.

Payment itself is deferred. The taxes fall due at the first certificate of occupancy, the point at which a building starts earning rent - a timing the founding memo notes matches recent state law, SB 937.

A waiver of $15,000 to $17,000 per unit sits against development costs of several hundred thousand dollars per unit. For midrise projects, though, feasibility is decided at exactly that margin - the case made in Building Through the Storm.

For the City, the founding memo does its own arithmetic. San José's recent subsidies to affordable development have averaged more than $200,000 per unit. The trade is one-time construction-tax revenue, money that would otherwise fund transportation projects, for construction activity now. The projected return is recurring: staff estimated $6.8 million a year in property taxes from roughly 10,000 new multifamily units, plus utility, business, and sales taxes.

Three structural facts separate this masterplan from the entitled projects still waiting. The August 2024 entitlement cleared CEQA for all 1,430 units in one action, so no later phase re-opens environmental review. The January 2025 land trade meant each developer carries only the dirt under its own product. And the incentive is sequenced to the phasing, so each building's waiver lands as that building moves toward construction.

What to watch

Milestones over the next 18 months, in rough order: vertical construction at Building B and Trimble Apartments beginning in the second half of 2026; sales activity at Pyrus Place, the new for-sale townhome product in North San José; Hanover Parkside's first occupancies in late 2027; and Building C's eventual construction start in 2027.

Frequently asked questions

How many homes will Coyote Creek Village have?

1,430 across three product types: 1,140 apartments in three market-rate buildings (397 in Hanover Parkside, 372 in Hanover Coyote Creek, 371 in Building C), 154 for-sale townhomes at Pyrus Place, and 136 units at Trimble Apartments, the affordable building. The plan also includes roughly 19,000 square feet of neighborhood retail, a 2.5-acre public park, and a parcel for a new municipal water well.

What affordable housing will the project include?

Two on-site mechanisms. Hanover's three market-rate buildings carry 57 income-restricted apartments - 20 in Parkside, 19 in Coyote Creek, 18 in Building C - at moderate-income rents, Building A's at or below 100% of area median income and Building B's at or below 110%. Trimble Apartments adds 135 restricted units for households earning 30% to 70% of AMI under a 55-year regulatory agreement. The townhomes comply through an in-lieu fee rather than on-site units.

What income levels qualify at Trimble Apartments?

The 135 restricted units span four tiers: 15 at 30% of area median income, 15 at 50%, 46 at 60%, and 59 at 70%. The mix is 64 one-bedroom, 37 two-bedroom, and 35 three-bedroom apartments. Proposed 2025 rents in the state application run from $1,130 for a 30% AMI one-bedroom to $3,656 for a 70% AMI three-bedroom, including utilities; final rents are set at placed-in-service under the regulatory agreement. Construction is expected to start in summer 2026, with completion anticipated in May 2028.

Are there below-market-rate townhomes at Pyrus Place?

No. SummerHill chose to pay the Inclusionary Housing Ordinance in-lieu fee rather than provide BMR units on site. The 154 townhomes are market-rate, in five plans from 1,355 to 2,315 square feet, pre-selling through a sales office at 675 Epic Way; a price sheet hasn't been published.

When will the first homes be ready?

Hanover Parkside (Building A) is under construction, with completion expected in the fourth quarter of 2027 and first occupancies to follow. Building B and Trimble Apartments are expected to start vertical construction in the second half of 2026, with Trimble's completion anticipated in May 2028. Pyrus Place townhomes are pre-selling now.

Notes on figures and sources

Several figures here are calculated, derived, or drawn from sources that disagree with one another. For transparency:

  1. Farmhouse relocation per San José Spotlight's coverage of the May 2025 groundbreaking and Local News Matters' May 2026 follow-up: the structure has completed its move to History Park, and preservation groups said at an April 30, 2026 event that an additional $300,000 is needed to renovate the interior with exhibits, an activity space, a gallery, and a staff office.
  2. Unit totals follow the June 23, 2026 Council memo (1,430 units; Buildings A/B/C at 397/372/371; 154 townhomes; 136 affordable units). Earlier documents and most press coverage cite 1,472 units and a 178-unit affordable building; figures in this post follow the most recent Council record throughout.
  3. Trimble Apartments timing follows the CTCAC/CDLAC staff report for CA-25-741, which anticipated construction from May 2026 to May 2028; site work is expected to begin this summer. No schedule has been published in City documents as of this writing.
  4. Land and loan figures ($78.6M site acquisition, $73.6M townhome parcel sale, $61.2M U.S. Bank financing, $120.4M JPMorgan Chase loan) follow Bay Area News Group reporting of Santa Clara County Recorder filings.
  5. "Roughly seven acres" reflects reported figures; the recorded parcel configuration may differ slightly.
  6. Employer, school, and transit distances are taken from SummerHill's Pyrus Place marketing materials and are not independently measured.
  7. Trimble Apartments award figures (bond allocation, tax credits, development costs, and financing sources) follow the CTCAC/CDLAC Project Staff Report for CA-25-741 and are application-stage estimates subject to CTCAC's final feasibility review at placed-in-service. The report lists an $8.6 million donated land value among the sources but does not identify the donor or the mechanism of the contribution. Unit-tier counts and proposed rents are the application's 2025 figures, stated as including utilities; final rents are set at placed-in-service under the regulatory agreement. The report's rent schedule lists the unrestricted manager's unit as a two-bedroom at $0 rent.
  8. AMI thresholds follow each building's Council approval (Building A at or below 100% AMI; Building B at or below 110%). Dollar income limits are published annually and change; consult the current published schedules rather than any figure quoted secondhand.
  9. Per-unit waiver figures are my calculation: each building's total waiver divided by its total unit count. Totals in the table are rounded to the dollar; Building A's approved figure is $6,057,536.80.

Sources

Questions or corrections? Reach me at kostya@kostya.io or LinkedIn.

Related Articles

Building Through the Storm: San José's Counter-Cyclical Housing Push
Beyond Zoning: Why 22,000 Entitled Homes Are Waiting
RISE / Berryessa TOD: Eleven Sources Behind a 195-Unit Affordable Tower
The BMR Pricing Formula