Total development cost: $175,017,919.1 That works out to $897,528 per unit including the two manager units, or $571,859 per unit in hard costs alone.2 The deal closed with eleven distinct funding sources3 stacked into a single capital structure, ranging from $51.9 million in tax credit equity down to $1.9 million in retained earnings.
The rest of this post walks through what those eleven sources look like, why they're structured the way they are, and what the structure says about how 100% affordable housing gets built in San José in 2026.
TL;DR: The RISE / Berryessa TOD Capital Stack
- Eleven sources, ~$175M: A 195-home, 100% affordable tower a quarter-mile from Berryessa BART, financed from eleven sources over 44 months.
- 24% debt, 76% subsidy: Senior debt and equity stacked with LIHTC, AHSC, and gap financing to close the cost-to-value gap.
- A template for affordable TOD: Shows how 100% affordable housing actually gets financed near transit in San José.
What's getting built
RISE is the first phase of a three-phase development on a four-acre site4 owned by the Santa Clara Valley Transportation Authority adjacent to the Berryessa Transit Center. The site previously served as construction staging for the BART extension. The affordable phase is ground-leased to Berryessa Affordable Housing, L.P., a partnership Affirmed Housing formed for the project. The future market-rate phases on the same site are, in the developer's words, "conceptualized" rather than entitled.
The unit mix:
- 50units at 30% AMI (extremely low income) - 49 supported by Project-Based Vouchers from Santa Clara County
- 92units at 50% AMI (very low income)
- 51units at 60% AMI (low income)
- 2unrestricted manager units
107 of the 195 units (55%) are 2-bedroom or 3-bedroom - what CTCAC classifies as a Large Family configuration. The 30% AMI tier includes permanent supportive housing units for formerly homeless residents, and the building includes on-site case management offices, community space, and children's play facilities. Community Solutions is the project's services provider. The Regulatory Agreement attached to the bond issuance carries a 55-year affordability covenant running through 2083.
Construction starts in May 2026. Substantial completion is scheduled for May 2028, with move-ins beginning in June 2028.10
The 44-month financing assembly
The community meetings, design iterations, and entitlement reviews are the part of the project that's visible to neighbors. The capital assembly is what determines whether 100% affordable projects actually break ground.
Tracked as a sequence:
- September 2022 - First community meeting (VTA and Affirmed introduce the project)
- June 2023 - Community meeting #2 covering design and the VTA station access study
- September 2023 - Planning entitlement submittal
- November 2024 - Entitlements approved
- October 2024 - Affordable Housing and Sustainable Communities (AHSC) award of approximately $38M for the project and King Road Complete Streets improvements
- May 13, 2025 - San José City Council approves a $9.9M construction-permanent loan from the Low and Moderate-Income Housing Asset Fund (File 25-499)
- May 20, 2025 - City and developer file joint application to the California Debt Limit Allocation Committee (CDLAC) and California Tax Credit Allocation Committee (CTCAC) for $82,584,672 in tax-exempt private activity bonds and 4% federal tax credits
- August 5, 2025 - CDLAC awards the bond allocation; CTCAC reserves the 4% credits
- November 13, 2025 - CDLAC grants a 60-day closing extension, moving the deadline from March to May 2026
- January 2026 - Building permits issued
- April 14, 2026 - City Council approves the bond issuance and related transaction documents (File 26-399)
- May 2026 - Groundbreaking
For this development, the key approvals and funding sources were closely linked and generally had to be secured in sequence. AHSC required a high level of readiness, including environmental review and a clear path to all necessary entitlements, which effectively pushed the major approvals early. A local loan commitment had to be in place before the city filed its bond application, and issuing the tax-exempt multifamily housing bonds then depended on receiving a state bond allocation. If any of these approvals or commitments had fallen through, the team would likely have needed to reapply in a later round, restructure the financing, or risk the project not proceeding. The April 2026 bond closing came roughly three and a half years after the first community meeting.
What is a Transit-Oriented Development (TOD) capital stack? A Transit-Oriented Development (TOD) capital stack is the multi-layered financial structure required to fund high-density housing near public transit hubs. Because urban infill TODs are structurally expensive to build, their capital stacks often require assembling traditional senior debt and developer equity alongside specialized public subsidies, tax credits (like LIHTC), and gap financing to achieve financial feasibility.
The eleven-source capital stack
| Source | Construction | Permanent |
|---|
During construction, the stack leans on debt. The 2026A bonds at $82.6 million carry nearly half of the construction sources, with a $25 million taxable construction loan from Deutsche Bank in the second position. Tax credit equity contributes $13.5 million of its eventual $51.9 million during this phase. The AHSC loan, contributed developer fee, and retained earnings haven't drawn down at all.
At conversion in May 2029, the structure flips. The bonds convert to a $42 million permanent note at a fixed 6.34% rate. Tax credit equity takes the largest position at $51.9 million. AHSC enters at $29 million. The construction loan disappears, repaid in full from the new permanent sources.
Of the $175 million in permanent capital, only the $42 million bond note is hard debt that has to be serviced by rental income. Tax credit equity requires no repayment. The four soft loans from City, County, BAHAF, and AHSC are typically repaid only from residual cash flow after operating expenses, hard debt service, and reserves are funded, meaning they may sit on the books for the full 55-year regulatory period without payment. The deferred developer fee is paid from project surplus over time. The bond interest earnings and retained earnings are accounting entries.
Roughly 24% of the cap stack is hard debt. The remaining 76% is subsidy in various forms.11 That ratio is what allows the 30% AMI rents (between $1,024 and $1,522 depending on bedroom count) to actually cover the building's operating costs.
$572K per unit, in context
Hard costs per unit work out to $571,859. Soft costs add another $205,000 per unit. Land and acquisition adds $58,500 per unit, covering ground lease execution and predevelopment expenses since VTA owns the dirt outright and Affirmed isn't buying it. The cash developer fee adds $62,000 per unit. The all-in basis: $897,528 per unit.
RISE is a California prevailing wage project: all construction workers are paid at California State Prevailing Wages or federal Davis-Bacon rates, whichever is higher, a standard the pre-construction community presentation lists among the project's community benefits.5 Prevailing wage typically adds a meaningful premium to hard costs relative to non-prevailing-wage market-rate construction.6 It's a programmatic feature of publicly-financed affordable housing, not an inefficiency.
The building is 10 stories on a 0.79-acre footprint, all-electric with rooftop solar, designed to GreenPoint Rated Gold standards, with case management offices, community space, bike parking, on-site property management, and children's play facilities. Each of these adds cost relative to a stripped-down market-rate build.
For context, the City's 2025 Cost of Development Study documents hard-cost ranges for high-density San José construction that put RISE's $572K per unit within the band you'd expect for an all-electric, prevailing-wage, family-sized affordable building delivered in 2026.7
AHSC's double duty
The AHSC grant for this project shows up as two different numbers in two different places. Affirmed’s October 2024 announcement says the project received about $38 million, while the City’s Sources & Uses table in Council File 26‑399 lists $29 million in the housing budget.
The gap, roughly $9 million, is the King Road Complete Streets work: new walking and biking improvements that better connect the Berryessa Transit Center to the surrounding neighborhood. AHSC is designed to fund both new affordable homes and the streets, paths, and transit access that make those homes work well.
So the housing pro forma only shows the $29 million that lands in the building’s capital stack, while the developer’s announcement references the full AHSC package of about $38 million for both the housing and the King Road improvements. That’s why AHSC projects so often come with visible street upgrades nearby: the program is built to pay for both.
TCAC scoring shaped the unit mix
The 4% federal Low‑Income Housing Tax Credit is the main source of long‑term financing for affordable housing in California. Even though it is often called “non‑competitive,” projects still effectively compete because the tax‑exempt bond authority they rely on is limited and scored by the state.
The scoring system gives extra points to “Large Family” projects, where most homes have two or more bedrooms. RISE meets that standard: about 55 percent of its 195 apartments are two‑ or three‑bedrooms (54 two‑bedrooms and 53 three‑bedrooms), compared with 45 studios and 43 one‑bedrooms.
Most 100% affordable projects skew studio- and one-bedroom-heavy to maximize unit count on a given site. Affirmed traded total unit count for unit size - fewer homes, but homes large enough for families. The CTCAC scoring math, which rewards the Large Family designation, is a direct driver of that design choice.
The lender protection clause
The council memo discloses a rent escalation provision built into the financing documents.
The lenders - Deutsche Bank as taxable construction lender, the public bondholders as 2026A purchasers, and the eventual permanent loan holder - required, as a condition of underwriting, that loan documents permit rents and income restrictions to rise to 30% of 60% AMI for new tenants under two specific scenarios: if Project-Based Voucher contracts expire or terminate, and if foreclosure occurs.
The memo states plainly that "without this approval, the other lenders making this request will not be able to underwrite their respective construction and permanent financing." Lenders are pricing tail risk that PBV contracts won't be renewed (PBV contracts are typically written for about 15–20 years, with extensions possible but always dependent on continued HUD funding) and want contractual mechanisms to maintain debt service capacity if renewal fails.
The provision does not change anything for current residents under their existing leases and subsidy agreements, and the 55‑year affordability covenant in the Regulatory Agreement still applies. It mainly illustrates how affordable housing loans are being structured in 2026: lenders are more cautious about long‑term subsidy risk and are seeking additional protections so the property can continue to cover its debt if federal contracts change in the future.
What this implies for Phase 2 and the next 100% affordable deal
RISE sits on Parcel B (0.80 acres) of a four-acre VTA-owned site. The remaining parcels:
- Parcel A (1.96 acres) - future market-rate office
- Parcel C (0.69 acres) - future market-rate apartments
- Parcel D (0.59 acres) - shared access and landscaping
RISE breaks ground because eleven funding sources aligned over four years. Market-rate housing phase will pencil only if rents in the Berryessa submarket support the math without subsidy. The office development sits further out still, given how soft the Bay Area office market has been. The same four-acre parcel ends up sequencing three financing approaches that have very little in common.
The broader San José pipeline mirrors that pattern. Market-rate production runs on Multifamily Housing and Downtown Residential Incentive Programs (covered in Building Through the Storm). 100% affordable production runs on AHSC, BAHAF, LIHTC, CDLAC, and County PBV, and City of San José's NOFA. The two pipelines don't share funding sources, don't always share approval processes, and don't share market constraints. They produce in parallel. A new federal layer arrived for 2027: the Little Portugal tracts a half-mile west of the station landed on the certified Opportunity Zones 2.0 map, which adds OZ equity to the menu for nearby market-rate phases — federal-only in California, as that piece prices out.
For the 100% affordable side specifically: AHSC is awarded competitively and demand regularly exceeds available funds.9 The 4% credit market is effectively limited by tax‑exempt bond volume, and BAHAF’s gap‑funding capacity is finite. A future RISE‑scale deal would need each of these layers to show up at roughly the same level; if any one program shrinks, even temporarily, projects either pencil only with more deferred fee and owner contribution—or they do not pencil at all.
Deal by deal
This is the first in an occasional series of project case studies — close looks at how individual San José developments actually get financed and built, across both the market-rate and affordable pipelines. Each one breaks down a real deal's capital stack, structure, and feasibility constraints — detail that usually stays buried in pro formas and council files. Since these run on no fixed schedule, sign up for The Inside Brief below to catch the next one.
Notes on figures and sources
Several figures in this analysis are calculated, derived, or drawn from sources that disagree with one another. For transparency:
- Total development cost of $175,017,919 reflects the Sources & Uses in Council File 26-399, Attachment B (Borrower proforma dated February 11, 2026).
- Per-unit figures ($897,528 all-in; $571,859 hard cost; and the per-category figures in the Uses breakdown) are calculated by dividing each line in Attachment B by 195 units, the full count including the two manager units.
- "Eleven sources" consolidates the 13-line Attachment B Sources table: the construction-phase bond and its permanent-phase note are a single instrument shown in two phases, and the deferred and contributed developer fees are a single developer contribution in two forms. Three of the resulting eleven - public bond interest earnings, deferred costs, and retained earnings - function as balancing entries rather than external capital.
- "Four-acre site" is the sum of the four VTA parcels in the pre-construction site plan (A: ~1.96 ac, B: ~0.80 ac, C: ~0.69 ac, D: ~0.59 ac ≈ 4.04 ac).
- Prevailing wage standard is documented in the VTA pre-construction presentation; both AHSC and the public bond financing carry prevailing-wage requirements.
- Prevailing wage cost premium is a general industry observation, not a project-specific figure. Published estimates of the premium vary by market, trade mix, and project type.
- Cost comparison to the 2025 Cost of Development Study is my own assessment, not a line-item reconciliation against that study's published ranges.
- AHSC infrastructure split: the ~$9M difference between the announced ~$38M award (developer's October 2024 update) and the $29M in the project's Sources & Uses is attributed to the King Road Complete Streets component. The exact split and the entity administering the infrastructure dollars are not specified in the public documents cited here.
- AHSC competitiveness is a general characterization of the program. Round-specific award and demand figures are published by the California Strategic Growth Council.
- Construction schedule (May 2026 start, May 2028 substantial completion) follows the VTA pre-construction presentation.
- The 24% / 76% debt-to-subsidy ratio is derived: the $42M permanent note as a share of the $175M total. The "subsidy" share groups tax credit equity, the four public soft loans, deferred fees, and balancing entries. Repayment terms for the soft loans are not detailed in the public financing documents; the residual-payment characterization reflects standard practice for loans of this type.
Sources
- City of San José Council File 26-399, April 14, 2026 - Authorization of Tax-Exempt Multifamily Housing Revenue Bonds Series 2026A and related documents, including Attachment B: Sources and Uses
- City of San José Council File 25-499, May 13, 2025 - Loan Commitment for Berryessa Station at 1565 Mabury Road
- California Debt Limit Allocation Committee bond allocation, August 5, 2025
- California Tax Credit Allocation Committee 4% credit reservation, August 2025
- California Strategic Growth Council AHSC award announcement, October 2024
- Berryessa TOD Apartments outreach site, Affirmed Housing
- VTA Berryessa TOD Pre-Construction Community Meeting Presentation, April 7, 2026
- City of San José 2025 Cost of Development Study
Questions or corrections? Reach me at kostya@kostya.io or LinkedIn.