This analysis draws on the 2025 Cost of Residential Development Study prepared by Economic & Planning Systems (EPS) and CSG Advisors for the City of San José. Numbers cited come directly from that report unless otherwise noted.
What is a real estate development feasibility gap? A housing feasibility gap is the economic deficit that occurs when a project's Residual Land Value drops below the cost to acquire the land. This happens when the total supportable project value (driven by local rents) is insufficient to cover the total development costs (hard construction, soft costs, and financing), causing new housing starts to stall.
$$\text{Residual Land Value} = \text{Total Supportable Value} - \text{Total Development Costs}$$
TL;DR: The San José Housing Feasibility Gap
- Entitlements aren't the bottleneck: ~22,000 units were entitled (2020–2024) but only ~7,000 pulled permits—the constraint is economic, not zoning.
- A residual-land-value problem: Projects stall when supportable value can't cover development costs, pushing residual land value below acquisition cost.
- From the City's own numbers: Quantified using the 2025 Cost of Residential Development Study (EPS / CSG) for San José.
The Gap Between Approval and Construction
Zoning reform dominates housing policy conversations. Upzone more land, remove parking minimums, streamline approvals—production will follow. That's the theory.
San José’s recent track record complicates that narrative. Between 2020 and 2024, the city entitled roughly 22,000 housing units, spanning single-family homes, large downtown towers, and everything in between. These projects cleared planning review, got their approvals, and sat down with their lenders. About 7,000 of those units pulled building permits. The other 15,000 remain in limbo, approved but not moving forward.
This isn't a zoning problem. These projects already have entitlements. The constraint is financial feasibility, whether expected revenues exceed expected costs by enough margin to justify the risk and attract capital.
The exceptions prove the point. The projects moving today are the ones whose economics clear by a different route: Coyote Creek Village, where most of the 1,430 homes at Montague and Seely are wood-frame products backed by city incentives, and the 168 affordable apartments approved next to The 88 in five months, where tax-credit financing replaces market-rate math entirely.
How Developers Evaluate Feasibility
The metric that matters is Residual Land Value (RLV). Start with what the completed project would sell or rent for. Subtract hard costs (construction), soft costs (architecture, permits, fees), and financing. What's left over is the residual or the amount theoretically available to pay for land.
The Feasibility Equation
Positive RLV means the project can proceed. Negative RLV means it can't, regardless of zoning. No developer will pay more for land than the project can support. When construction costs jumped roughly 40% over the past five years while rents grew more slowly, projects that penciled out in 2019 stopped working.
What's Feasible and What Isn't
The EPS/CSG study modeled five building types across San José's submarkets: townhomes, stacked flats, podium apartments, wrap apartments, and high-rise towers. The results split cleanly.
Wood-Frame Works
Townhomes and stacked flats show positive RLV across nearly every location. Construction costs run around $266 per square foot. Parking is tuck-under at roughly $14,000 per space. The math works without subsidies or incentives.
High-Rise Doesn't
Residential towers face different economics. face different economics. Steel-frame construction costs about $560 per square foot. Structured parking adds another $80,000+ per space. The study found downtown towers showing negative RLV of approximately $285,000 per unit. Achieving feasibility would require rents to increase 30–35% (from current levels around $4.25/SF to roughly $5.70/SF).
Mid-Rise Is the Margin
Podium and wrap buildings sit at the tipping point. These show negative RLV, but marginally. A 5-15% improvement in market conditions—through rent growth, cost reductions, or fee waivers—could flip them to feasible. This is where policy intervention has the highest leverage.
Feasibility by Building Type
Central San José Submarket Analysis
| Type | Viability Score | RLV / Unit | Gap to Close |
|---|---|---|---|
| Townhome | +$57k | Feasible | |
| Stacked Flat | +$25k | Feasible | |
| Wrap | −$53k | 5–10% gap | |
| Podium | −$69k | 10–15% gap | |
| Tower | −$287k | 30–35% gap |
Check Your Project
Use this tool to see how feasibility varies by building type and location, based on the study's findings.
Feasibility Calculator
Based on 2025 EPS Study Data
Policy Implications
The study's findings point toward a more surgical approach to housing incentives.
Don't spend resources on what already works. Townhomes and stacked flats pencil out. Fee waivers or density bonuses for these products are giveaways, not catalysts. Let the market build them.
Focus incentives on the margin. Wrap and podium buildings are 5–15% away from feasibility. Impact fee waivers, reduced parking requirements, or modest subsidies could tip these projects. This is high-leverage territory. The federal map just moved the same direction: Opportunity Zones 2.0 put 17 San José tracts on the 2027 map, a source of patient equity aimed at exactly this margin.
Accept that towers need a market shift. Downtown high-rises are 30–35% underwater. No realistic fee waiver closes that gap. These projects need either a significant rent increase (unlikely in the short-term), a major construction cost reduction (requires industry-wide change), or deep subsidy (expensive). Until one of those happens, towers will remain on paper.
There is one more path for a tower that already got built and stalled: the city stepping in on the demand side. That is the story of The Fay, where San José master-leased 197 units in a distressed downtown high-rise — now renting to middle-income households through LIVE San José at Flow.
Reconsider the zoning-first frame. San José already entitled 22,000 units that aren't getting built. More entitlements won't solve a feasibility problem. Policy energy might be better spent on reducing soft costs, streamlining building permits (not just planning approvals), or targeting incentives where they'll actually move projects.
Summary
- 68% of entitled units haven't pulled permits. Approvals aren't the constraint—economics are.
- Wood-frame construction is viable. Townhomes and stacked flats work without help.
- Mid-rise is the policy opportunity. Wrap and podium buildings need 5–15% improvement. Targeted incentives can make a difference.
- Towers need patience or deep subsidy. A 30–35% gap isn't something fee waivers solve.
Questions or corrections? Reach me at kostya@kostya.io or LinkedIn.
Coyote Creek Village: What's Being Built at Montague and Seely
RISE / Berryessa TOD: Eleven Sources Behind a 195-Unit Affordable Tower
What's Being Built Next to The 88: 168 Affordable Homes at Second and the Paseo
Work Here, Live Here: Subsidized Workforce Housing in Downtown San José
Kostya.io