- What's being built 168 apartments on a 1.34-acre parking lot at South 2nd Street and Paseo de San Antonio, 166 of them restricted to households earning 30–80% of area median income. The Site Development Permit was approved September 4, 2026.
- Who's behind it Sobrato owns the land; Pacific West Communities (The Pacific Companies) is the developer; AO is the architect. Seven stories over a two-level podium with 153 parking spaces, across the street from the Paseo de San Antonio light rail station.
- Where the rents land The building's center of gravity is the 60% AMI tier — 100 of the 166 restricted units. A one-bedroom there rents for about $2,466 to a household earning up to $98,640. Sixteen units sit at the deepest 30% tier.
- Twice planned, never built The lot was phase two of CIM Group's Central Place plan in 2005 and the site of Sobrato's 23-story, 399-unit tower proposal in 2015. Neither was built.
- The density bonus twist The project invoked the State Density Bonus Law for three design incentives and took no additional units. On a site zoned for roughly 1,072 homes, density was never the constraint.
On September 4, San José's Planning Director signed a Site Development Permit for the parking lot at 0 South Second Street: 1.34 acres between the 22-story 88 and the Hammer Theatre, a block from San José State. The permit allows a seven-story building with 168 apartments, all but two of them deed-restricted for households earning between 30% and 80% of area median income.
The lot has been planned before. In February 2005, CIM Group's agreement with the San José Redevelopment Agency described Central Place as a two-phase project: a 23-story condominium tower first and a second tower after it, with the Agency putting $35.35 million into a $240 million deal and taking 30% of the profits.3 The first tower opened in 2008 as The 88. The second never started, and the phase-two land stayed a surface lot. Sobrato bought it in 2010, and in October 2015 filed a preliminary concept for a 23-story, 399-unit apartment tower designed by Arquitectonica.4 "With the trend that downtown is on, and the success that [other developers are] seeing, I think it will make sense to build it by the time we have the project permitted and ready to go," Rob Hollister, Sobrato's president of real estate, told the Silicon Valley Business Journal. The quote was a bet on timing: entitle the tower now, and let downtown rents grow into its construction costs by the time it was ready to build. They never did. By 2018 the application was still pending,4 and it never reached a hearing.
The building approved this month is a different product for a different market. The General Plan's Downtown designation allows 800 units an acre on this site, which works out to 1,072 base units before any density bonus. The approved project is 168 units, at 125 units an acre. The arithmetic behind the gap is the subject of Beyond Zoning: the City's 2025 cost study put downtown towers roughly $285,000 per unit short of feasibility, a hole no fee waiver fills. What follows is the building that is going ahead instead.
The block
Stand at the corner of South 2nd and the Paseo de San Antonio and walk the lot clockwise. On the north property line is The 88: 22 stories, 197 condominiums, completed in 2008 by CIM Group with Wilson Meany Sullivan, the tallest residential building in the city when it opened.2 Between the tower and the lot runs Central Place, a private drive off both South 2nd and South 3rd that will serve as the new building's vehicle entrance and trash staging area, and that gives the project its working name, Second Street & Central Place Apartments. East across South 3rd is Paseo Plaza, 210 condominiums in six stories completed in 1997, which the staff report cites as the height the new building steps down toward.
South of the lot is the Paseo itself, and across it the Hammer Theatre, run by San José State since 2016; its main hall is the Sobrato Auditorium. The applicant describes the new building as "directly connected" to the plaza, with a glass-fronted, retail-scaled corner at the Paseo and the residential lobby on South 3rd.
West across South 2nd is the southbound platform of the Paseo de San Antonio light rail station, with bus lines 66, 68, 201, 202, Rapid 523, and Rapid 568 stopping at the corner. South 2nd here is part of the Downtown Transit Mall, which is why one of the permit's conditions requires the developer to preserve, and if damaged replace, the granite pavers and granite curb along the frontage.
What's being built
The building is 238,775 gross square feet: 163,600 of residential floor area over 75,175 of structured parking and building services, which is to say that 31% of the building is the podium.5 Five floors of Type III wood framing sit on two levels of Type I-A concrete, for a total height of 80 feet 4 inches; there is no setback requirement in the DC Downtown Commercial zone, and the height limit is the airport's, not the City's. The podium is naturally ventilated, a decision that shows up again below in the Density Bonus request.
The approved plans, dated June 26, 2026, carry 123 one-bedroom, 33 two-bedroom, and 10 three-bedroom apartments, plus two two-bedroom manager's units. One-bedrooms are 73% of the building. For comparison, Trimble Apartments, the same developer's 136-unit affordable building at Coyote Creek Village in North San José, is 47% one-bedroom; this is a downtown product for one- and two-person households. The mix moved during review. The February 2026 plan set showed 138 one-bedrooms, 25 two-bedrooms, and 10 three-bedrooms with 145 parking stalls; the SB 330 preliminary application in April was reported at 173 units; the approved set trades 15 one-bedrooms for 10 more two-bedrooms.5
Resident amenities are a gym, a reading room, a roughly 1,700-square-foot lounge and event room at ground level, and a landscaped courtyard on the podium deck facing South 2nd. There are 44 bicycle spaces against 42 required, long-term in a ground-floor bike room and short-term racks in the right-of-way along South 2nd, Central Place, and the Paseo. The garage holds 153 cars and four motorcycles. Trees go into the courtyard and two palms onto Central Place. The exterior is brick veneer at the ground floor and second story, stucco and vertical siding above, and metal awnings on every frontage; the staff report credits the brick with breaking up the mass at the pedestrian level and the material changes with distinguishing the building's volumes.
Who qualifies, and what they pay
The applicant's tier table puts 16 units at 30% of area median income, 16 at 50%, 100 at 60%, and 34 at 80%.1 The table below translates those tiers into 2026 dollars using the HCD income limits for Santa Clara County that took effect June 23, with a one-bedroom mapped to a two-person household, a two-bedroom to three, and a three-bedroom to four. Rent is 30% of the tier income divided by twelve, gross, before the utility allowance.6
| Unit | AMI tier | Units | Household income up to | Max gross rent |
|---|---|---|---|---|
| 1 bedroom | 30% | 12 | $49,350 | $1,234 |
| 1 bedroom | 50% | 12 | $82,200 | $2,055 |
| 1 bedroom | 60% | 74 | $98,640 | $2,466 |
| 1 bedroom | 80% | 25 | $129,950 | $3,249 |
| 2 bedroom | 30% | 3 | $55,500 | $1,388 |
| 2 bedroom | 50% | 3 | $92,500 | $2,313 |
| 2 bedroom | 60% | 20 | $111,000 | $2,775 |
| 2 bedroom | 80% | 7 | $146,200 | $3,655 |
| 3 bedroom | 30% | 1 | $61,650 | $1,541 |
| 3 bedroom | 50% | 1 | $102,750 | $2,569 |
| 3 bedroom | 60% | 6 | $123,300 | $3,083 |
| 3 bedroom | 80% | 2 | $162,400 | $4,060 |
| 2 bedroom (manager's) | — | 2 | unrestricted | — |
| Total | 168 |
Income limits are HCD's 2026 figures for Santa Clara County; rents are calculated, not published. See note 6 for the method and for the CTCAC alternative.
Three things stand out in the table. The building's center of gravity is the 60% tier: 100 of the 166 restricted units, and a one-bedroom there rents for $2,466 to a household earning up to $98,640, a band that takes in a large share of downtown's service, hospitality, and entry-level public-sector workers. The 30% tier, where the discount to market is largest, is 16 units. And the 34 units at 80% AMI carry ceilings of $3,249 for a one-bedroom and $3,655 for a two, in the same general range as the newer apartment buildings downtown. Rents at that tier give the building a stable income base, which is part of what makes the deeper tiers possible under the same roof. The 2026 income limits post covers this year's rent and income levels across the Bay Area in detail.
One arithmetic note for readers who underwrite these deals: the cover-letter mix averages 60.2% AMI across the 166 restricted units, and a unit or two may shift tiers as the financing comes together.6
The Density Bonus that added no density
The project applied under the State Density Bonus Law, and the staff report walks through the entitlement: with 33 very-low-income and 133 low-income units, the project qualifies for a 50% density bonus, or 84 additional units, and for four incentives or concessions.8 It took none of the units. It requested no waivers of development standards, which a project of this kind can request without limit. What it did request were three incentives, each aimed at a provision of the Downtown Design Standards and Guidelines.
Building placement. The Guidelines call for a ground-level facade along 70% of each public-facing property line. Complying, the staff report says, would have confined the building to a portion of the site and cost roughly 20 units, raising the land cost per unit and adding what the report describes as "$600 per unit per year" in lease burden. The economics in the record are thin here, and the report leans on the statute's presumption: a cost-reducing incentive is deemed to help make the committed affordable units feasible.
Arrangement of activities. The Guidelines prioritize active uses at intersections, paseos, plazas, and transit stops, and the South 3rd frontage does not meet the percentage. The reason is the garage. Wrapping it in active space would enclose it and require mechanical ventilation, "over $100,000 to install" plus fans that run for the life of the building, on a property whose rents are capped. So the podium breathes through louvers, South 3rd gets a lobby and loading rather than storefronts, and the active frontage concentrates at the Paseo corner where it counts most. This is the incentive that shapes the building.
Skyline lighting. The Guidelines ask for coordinated lighting at the skyline, podium, and pedestrian levels. Dropping the skyline component saves the lighting engineer's scope, the fixtures, and the electricity, about $30,000.
The three requests have a common shape. On a lot the General Plan zones for 1,072 units, density was not the constraint; the design standards were, and the Density Bonus Law was the instrument for relief from them. Under Government Code 65915, once a project qualifies, the City must grant a requested incentive unless it makes written findings that the incentive is not needed to make the affordable units feasible, that it would cause a specific adverse impact on public health, safety, or a listed historic property, or that it would violate state or federal law. Staff made no such findings, and the incentives were approved as part of the permit.
On parking: San José has no minimum parking requirement, and the light rail platform is across the street. Even so, lenders and tenants alike still expect a downtown building to come with spaces, and the project provides them — 153 stalls, 0.91 per unit, in the two-level structured podium.
A few conditions of approval are worth noting: Saturday concrete pours for the podium deck are allowed, with truck traffic confined to South 3rd; the developer must sign a crane agreement with the Airport Department, since the crane, not the building, breaks the downtown height limits; and the Fire Department has flagged a fire-access item at the zero lot line, deferred to building-permit review — the one open design item in the file.
The fee stack
The parks memo in the permit file is a worked example of how San José's fee schedule treats a 100% affordable project. The Park Impact Ordinance obligation for 168 units, computed at three acres of parkland per thousand residents, is 1.179 acres of dedication or an in-lieu fee. The memo runs the fee from gross to net:7
| Park impact in-lieu fee | Amount | |
|---|---|---|
| A | Gross fee, 168 units ($22,600 per unit) | $3,796,800 |
| B | Affordable housing reduction, 50% per unit on 166 restricted units | −$1,875,800 |
| C | Adjusted fee | $1,921,000 |
| D | Private recreation credit, if ~15,412 sq ft of qualifying amenities (50% cap) | −$576,300 |
| E | Net fee due to the City | $1,344,700 |
| Per unit, net9 | $8,004 |
The two manager's units do not qualify for the affordable reduction unless they are deed-restricted, and the private recreation credit is applied for separately, usually after entitlement; the memo's figures are a preliminary estimate. What is not preliminary is the timing. Under SB 937, effective January 1, 2025, a project that is 100% affordable or eligible for a state density bonus (this one is both) pays its park fees at final inspection or certificate of occupancy, or five years after the building permit if construction has not begun, rather than at permit issuance. The memo confirms the project qualifies. The City's own incentive programs adopted the same certificate-of-occupancy timing for construction taxes, as the MHIP memos note, so state law and local program now point the same direction.
The rest of the stack in one pass. The Inclusionary Housing Ordinance is satisfied through its 100% affordable option: a City deed restriction on every unit but the manager's, with the Inclusionary Housing Agreement recorded senior to all deeds of trust before the first building permit. The project is exempt from a transportation demand management plan for the same reason. The file is silent on construction taxes, and the project does not appear on the Multifamily Housing Incentive Program's list of eligible projects. It will pay the Downtown Property-Based Improvement District assessment, $0.1198 per square foot of building and lot area on residential parcels in the current tax year, for the ambassadors and clean teams on the Paseo. It contributes $5,000 toward camera and signal upgrades at San Fernando and 2nd. And because the site is inside the Downtown Strategy 2040 boundary, whose environmental impact report already concluded that development here has less-than-significant transportation impacts, the project's traffic work was a Local Transportation Analysis memo rather than a new study, and its environmental clearance is a Class 32 infill exemption rather than a negative declaration.
What the file does not contain is a capital stack. There is no information about a state bond or tax credit award, no City Notice of Funding Availability commitment, no County funding identified. The financing is the next act, and two recent San José affordable deals bracket the range. Trimble Apartments, by the same developer, was awarded tax-exempt bonds and 4% credits in December 2025 on a stack of bond debt, credit equity, deferred developer fee, and donated land, with no City soft loan and an all-in cost of $851,879 per unit. RISE / Berryessa, the fully subsidized version, ran $897,528 per unit across eleven sources, four of them public.
How it got approved in five months
The sequence, from the first plan on the lot to the permit:
- February 2005 – CIM Group's Central Place agreement with the Redevelopment Agency: two towers in two phases, $240 million, $35.35 million from the Agency
- November 2005 – 2008 – The 88 built; phase two never starts
- 2010 – Sobrato buys the phase-two lot10
- October 2015 – Sobrato files a preliminary concept for a 23-story, 399-unit apartment tower
- 2018 – The tower's Site Development Permit application is still pending
- February 20, 2026 – AO plan set for Pacific West: seven stories, 168 units, 145 stalls
- April 2026 – SB 330 preliminary application filed, vesting the zoning and capping the number of hearings
- June 19, 2026 – On-site notice signs posted on South 2nd and South 3rd
- June 26, 2026 – Approved plan set (third submittal)
- July 22, 2026 – Community meeting, by Zoom, for owners and tenants within 1,000 feet
- July 28, 2026 – Parks Department response to the third submittal
- September 3, 2026 – Director's hearing
- September 4, 2026 – Permit issued
Roughly five months separate the SB 330 preliminary application from the permit. Four things made that possible, and none of them is unique to this site. Environmental clearance was a Class 32 infill exemption, with transportation already covered by the Downtown Strategy 2040 EIR, so no project-level environmental document was needed. SB 330 vested the rules in place at application and capped the process at five hearings. The Density Bonus incentives had to be granted absent specific findings. And a Site Development Permit for a project consistent with its zoning is a Planning Director decision: no Planning Commission, no City Council, unless someone appeals. The 2015 tower never got to a hearing at all.
The permit is not a building permit. Before one can issue, the developer must take its construction plans through plan check, record a Density Bonus regulatory agreement, record the Inclusionary Housing Agreement, grant an avigation easement to the City, obtain an FAA Determination of No Hazard for each building high point, sign the crane agreement, clear Public Works, and resolve the fire-access item. The permit expires in two years if construction has not commenced, in September 2028; the SB 330 vesting runs two and a half years from final approval.
What to watch
In rough order: a financing announcement, a building permit, and a construction start ahead of the September 2028 permit expiration.
Frequently asked questions
The project
How many homes are being built at 0 South Second Street?
168 apartments in a seven-story building: 123 one-bedrooms, 33 two-bedrooms, 10 three-bedrooms, and two two-bedroom manager's units. 166 of the 168 are deed-restricted for households earning 30% to 80% of area median income. The Site Development Permit (H26-013) was approved by the Planning Director on September 4, 2026.
Why is it seven stories when the site allows a tower?
The General Plan's Downtown designation allows up to 800 units per acre, or roughly 1,072 base units on the 1.34-acre site. The approved project is 168 units, about 125 per acre. Downtown high-rise construction has not been financially feasible in recent years; the City's 2025 cost study found downtown towers roughly $285,000 per unit short of feasibility. A 100% affordable wood-frame podium building is financed through a different capital stack that does not depend on market-rate rents.
Affordability and eligibility
Who qualifies to live there, and what will rent be?
Units are restricted at 30%, 50%, 60%, and 80% of area median income. Under the 2026 Santa Clara County limits, a one-bedroom at 30% AMI serves a two-person household earning up to $49,350 at a maximum gross rent of about $1,234; at 60% AMI, up to $98,640 and about $2,466; at 80% AMI, up to $129,950 and about $3,249. Final rents are set under the recorded regulatory agreement, and eligibility is confirmed by the property manager when leasing begins.
History and timing
Is this the tower Sobrato announced in 2015?
No. In October 2015 Sobrato filed a preliminary concept for a 23-story, 399-unit apartment tower at 150 S. Second Street, designed by Arquitectonica. That application was still pending in 2018 and never reached a hearing. The approved project is a seven-story, 168-unit, 100% affordable building developed by Pacific West Communities on Sobrato's land.
When will it open?
No construction schedule has been published. The permit expires in September 2028 if construction has not started, and the project still needs to record its Density Bonus and Inclusionary Housing agreements, obtain FAA clearance and an airport crane agreement, resolve a fire-access item, and secure financing before a building permit is issued.
Notes on figures and sources
Several figures here are calculated, derived, or drawn from sources that disagree with one another. For transparency:
- Tier counts follow the applicant's cover letter to the Housing Department, the only document in the file that breaks units down by bedroom count and tier. Its totals are 32 very-low-income units (30% and 50% AMI) and 134 low-income units (60% and 80%); the Director's permit and the Parks memo state 33 and 133. The one-unit difference does not change the rent table's structure.
- The 88 is listed at 22 floors and 197 units by Wikipedia and the CTBUH Skyscraper Center; a brokerage site says 23 floors. Roof height is reported at 286 feet (Wikipedia, SkyscraperPage) and 268 feet (CTBUH). This post uses 22 stories and does not repeat the claim that the tower was taller than City Hall, which turns on the disputed figure. "Tallest residential building in the city when it opened" is the form the sources support.
- Central Place deal terms ($240 million project, $35.35 million Redevelopment Agency investment, 30% profit share, two phases) follow the Mercury News's February 18, 2005 report as republished by SecurityInfoWatch. Hoge Fenton's 2018 downtown tour notes describe The 88 as a $276 million project; Wikipedia lists a $114.5 million construction cost. The 2005 figures are used because they describe the two-phase structure that put the second tower on this lot. A brokerage listing describes the never-built second phase as 22 stories with 204 units and 37,000 square feet of retail; those figures are not independently confirmed and are not used above.
- The 2015 tower is 23 stories and 399 units in Sobrato's October 19, 2015 release, which reprints the Silicon Valley Business Journal's report, and in The San Jose Blog's coverage that month; SF YIMBY's 2026 account gives 24 stories and 393 units. Its location on this lot rests on four sources: Sobrato's address for the project, 150 S. Second Street; The San Jose Blog's description of the site as "between The 88 and the building formerly known as The Rep"; Hoge Fenton's 2018 identification of "Sobrato Block 3, the parking lot adjacent to the Repertory Theater and The 88" as the site of the pending 399-unit application; and SF YIMBY's 2026 report treating it as the prior proposal for the same parcel. The Hollister quotation is as reprinted in the Sobrato release.
- Building area and the earlier unit mix come from the February 20, 2026 plan set, sheets A1.1 through A1.3, whose project data block lists 238,775 gross square feet and a mix of 138 / 25 / 10. That breakdown sums to 173 while the same block states a total of "±168 units"; the discrepancy is the plan set's. Approved-plan figures (168 units; 123 / 33 / 10 plus two manager's units; 153 stalls) follow the Director's permit and the applicant's cover letter. Area figures may have shifted slightly in the June 26 set.
- Rent and income figures are calculated, not published. Income limits are HCD's 2026 Official State Income Limits for Santa Clara County; household size is mapped per Health and Safety Code section 50052.5(h). HCD does not publish a 60% tier; it is computed here as 120% of the very-low limit, HUD's multifamily tax subsidy method, which lands within $30 of a straight 60% of median at every household size. Rent is 30% of income divided by twelve, gross of utilities. If the project is financed through CTCAC, its rents will follow TCAC's schedule, which assumes 1.5 persons per bedroom; under that method the 60% one-bedroom ceiling is about $2,312 and the 60% three-bedroom about $3,206. The 60.2% weighted average is the sum of each restricted unit's tier percentage divided by 166.
- Park fee figures follow the Department of Parks, Recreation and Neighborhood Services memo of July 28, 2026, which labels them a preliminary estimate subject to change at approval; the affordable reduction assumes the Housing Department verifies 166 qualifying units, and the private recreation credit assumes the applicant provides and is approved for roughly 15,412 square feet of qualifying amenities. The $22,600 per-unit gross is the memo's total divided by 168; the ordinance's schedule is weighted by unit type and occupancy, so the per-unit figure is a derived average.
- Density bonus entitlement as stated in the permit: a 50% bonus under Government Code section 65915(f)(2) and four incentives. For a project that is 100% affordable apart from manager's units, section 65915(f)(4) provides an 80% bonus and, within half a mile of a major transit stop, no maximum density at all. The distinction is academic here, since the project uses none of the bonus.
- Per-unit and percentage figures throughout ($8,004 net park fee per unit; 0.91 spaces per unit; 73% one-bedroom; 31% podium share) are my calculations from the figures in the permit file.
- Sobrato's 2010 purchase follows The San Jose Blog's October 2015 report that the company "purchased the land in 2010." The seller is not identified there; the 2005 agreement's provision allowing the City to find an alternate developer for phase two suggests the Redevelopment Agency controlled the parcel, but the recorded transfer has not been checked for this post.
Sources
- City of San José, Planning, Building and Code Enforcement – Site Development Permit, File Nos. H26-013 & ER26-063, 0 South Second Street (APN 467-22-160), issued September 4, 2026, with conditions of approval
- City of San José, Department of Parks, Recreation and Neighborhood Services – Response to Application and Plan Set dated 6/26/2026, Site Development Permit H26-013, third submittal, July 28, 2026, including the SB 937 Parkland Agreement template
- Pacific West Communities, Inc. – Entitlement application cover letter to the City of San José Housing Department, 100% Affordable Housing Development at 0 South 2nd Street (Planning File No. H26-013)
- AO – "Sobrato Apts, San Jose, CA," plan set dated February 20, 2026 (sheets A1.0–A1.8), for The Pacific Companies; approved plans entitled "S. Second St. & Central Pl. Apts." dated June 26, 2026
- The Sobrato Organization, "Sobrato moving forward with downtown San Jose high-rise," reprinting the Silicon Valley Business Journal, October 19, 2015
- The San Jose Blog, "Sobrato Planning Downtown San Jose Residential High-rise!," October 2015
- Hoge Fenton, 2018 Downtown San José Development Tour Notes (Sobrato Block 3; The 88)
- The Mercury News, "Two Condominium Towers Planned for San Jose, Calif.," February 18, 2005, as republished by SecurityInfoWatch
- SF YIMBY, "Preliminary Permits for 143 South Third Street, Downtown San Jose," April 2026
- Hoodline, "Downtown San Jose Parking Lot On Track To Become 171 Affordable Apartments," April 2026
- The Registry, "Sobrato, Pacific Companies Plan 173-Unit Affordable Project on Downtown San Jose Parking Lot," May 15, 2026, and "San Jose Planners Recommend Approval of Sobrato, Pacific West's 168-Unit Downtown Affordable Tower," August 2026
- The Real Deal, "Sobrato, Pacific West pitch affordable housing in downtown San Jose," April 27, 2026, and "Sobrato, Pacific West near approval for San Jose housing," August 31, 2026
- The Mercury News, coverage of the proposal, May 8, 2026, and coverage of the approval, September 2, 2026
- Council on Tall Buildings and Urban Habitat, The 88, Skyscraper Center; The 88 (San Jose), Wikipedia; Hammer Theatre, Wikipedia
- California Department of Housing and Community Development, Official State Income Limits 2026, effective June 23, 2026
- California Government Code section 65915 (Density Bonus Law); SB 330 (2019), Housing Crisis Act; SB 937 (2024), development fee deferral
Questions or corrections? Reach me at kostya@kostya.io or LinkedIn.
Beyond Zoning: Why 22,000 Entitled Homes Are Waiting
Coyote Creek Village: What's Being Built at Montague and Seely
The 2026 Income Limits Split the Bay Area Three Ways
RISE / Berryessa TOD: Eleven Sources Behind a 195-Unit Affordable Tower